Friday 19 April 2024
Select a region
News

Government answer to foreshore mystery all at sea

Government answer to foreshore mystery all at sea

Friday 15 November 2019

Government answer to foreshore mystery all at sea

Friday 15 November 2019


The Government’s answer to costly confusion over an elusive strip of publicly-owned coastal land is slowly being swept away, as the deadline for a key report has now been pushed back another four months, with the allotted budget already 70% gone on lawyers' fees.

The report is supposed to determine once and for all where the ‘foreshore’ begins and ends, even though the government has so far pursued several homeowners for substantial encroachment fines.

Infrastructure Minister Deputy Kevin Lewis committed in a Scrutiny hearing that the report would be published in January 2020. But according to the answer to a Freedom of Information (FoI) request, the review which promises the end to all the confusion, has now been pushed back another four months until at least April next year.

The Government say that the delay is due to the availability of the department’s lawyer...and the realisation that the project is actually more complicated than first anticipated.

Even the April estimate is being described as a “flexible” deadline.

The FoI response also says that £17,000 of the £24,000 budget has already been spent - which the government clarified has gone on conveyancer's fees - but the response also says that so far the Terms of Reference for the report have still not been agreed, a point later denied by the government. 

Jersey aerial 850x500

Pictured: The Government say that the review is more complicated than first thought.

When asked about the delay, a Government spokesperson said: “The review of the Foreshore Encroachment Policy is delayed due to two factors associated with the work in researching the land-side boundary of the foreshore – Officer resource and the uncertain nature of the research/investigation.

“The research of conveyancing contracts, historic seawall drawings and other documents/Acts is a service provided by the Law Officers’ Department. It has been necessary for the LOD to engage a conveyancer on a contract basis to carry out the bulk of the work. The contract conveyancer’s availability has varied from month to month, which has impacted on the programme.

“The second factor is that the first level of research has, in some stretches of the foreshore, identified the need for further investigation work and site visits, including land surveyor work. With the nature of the task, it is impossible to predict the extent of the foreshore where a greater level of more detailed research will be needed.”

Kevin_lewis_foreshore.jpg

Pictured: The Infrastructure Minister's commitment to a January publication date has been scuppered.

The longstanding crisis over the foreshore was brought to light when Express revealed the struggles of two coastal homeowners – Alan Luce and Julian Mallinson – who were slapped with hefty fines from Jersey Properties Holdings (JPH) when they tried to sell up due to claims that their houses were built on public land.

Long-contested and vaguely defined as the area of land “lying between the low water mark and the high water mark of the full spring tide,” disputes over the foreshore have prompted the Government to carry out a review to assess where exactly the boundary between public and private land lies.

The problems arose when the Queen – who originally owned the foreshore and seabed – gifting the land back to ‘the public’ in 2015. Following this, JPH have pursued financial recompense from owners of seaside property, even if the building was on the foreshore before the land was gifted back to the people of Jersey.

foreshore_Alan_julian.jpg

Pictured: The two coastal homeowners Alan Luce (left) and Julian Mallinson (right) whose plight thrust the foreshore issue into the public eye.

The Government ‘Landside Boundary Review’ was begun in the first quarter of this year as a joint project between JPH and the Law Officers’ Department, but there is some confusion about whether the official scope of the project has been finalised before work commenced.

In the FoI response which brought the review’s delay to light, it says that the terms of reference for the project couldn’t be provided as “they have not been finalised." 

However, when Express put this to the Government, this was contradicted by a spokesperson who said that the terms had indeed been finalised. 

Express has sought clarification about this discrepancy and is awaiting a response.

Campaign group, Save Our Shoreline has recently published a report on the saga, which calls for the Chief Minister to apologise to the Queen over the way her gift has been used, to stop pursuing islanders for fines relating to an ill-defined area, and to grant an amnesty to islanders who may be involved. 

READ MORE from Express on the foreshore...

Sign up to newsletter

 

Comments

Comments on this story express the views of the commentator only, not Bailiwick Publishing. We are unable to guarantee the accuracy of any of those comments.

You have landed on the Bailiwick Express website, however it appears you are based in . Would you like to stay on the site, or visit the site?