Monday 14 October 2024
Select a region
News

WATCH: Ports face pressure as construction imports rise

WATCH: Ports face pressure as construction imports rise

Friday 03 December 2021

WATCH: Ports face pressure as construction imports rise

Friday 03 December 2021


Jersey's harbour would be put under pressure and major changes would be needed to increase capacity if Jersey is forced to import more construction materials in future rather than producing them on-island.

Steve Tanner, Group Capital Projects Director, said capacity may be able to be increased under the 'Masterplan' to redesign parts of the harbour zone, but that it wouldn’t be able to cope with importation levels of 260,000 tonnes of aggregates per year if local production ceased.

Discussions are currently underway about the future provision of sand and aggregate, key materials for the construction industry.

The only provider of building sand in Jersey, Simon Sands recently suspended excavations at St. Ouen’s Bay because high construction demand had exhausted reserves quicker than expected and the Government had not extended its licence to extract fresh material.

Meanwhile, debate is raging as to whether the expansion of Granite Products’ quarry at La Gigoulande should go ahead - something neighbouring residents are strongly opposing.

Both issues have led to warnings from the construction industry that, if Jersey cannot get such materials locally, delays and cost rises will result.

La Gigoulande.jpg 

Pictured: Discussions about whether La Gigoulande Quarry should be expanded are underway.

On Wednesday, Chartered Town Planner Jeff Salt looked into the proposed extension of quarries and discussed the potential financial, environmental and practical issues that would arise from local production ceasing during one of the public meetings  held as part of the ‘examination in public’ of the three-year ‘bridging’ Island Plan.

Mr Tanner explained that Ports of Jersey are currently able to deal with the demand for sand, which is imported through bulk bags and thus does not require a dry plant. In addition, he said Ports of Jersey had planned on the assumption that 60,000 to 70,000 tonnes of sand would need to be imported if there was no on island production

“In reality the volume of sand that is being imported at the moment and is likely to be imported in the foreseeable future is something that we can handle,” he said. “We don’t do it in the most desirable and operationally efficient way just because of the nature of the infrastructure. 

“However our own infrastructure plans did make assumptions with respect to sand ceasing from an on-island production in 2023 anyway, so we are preparing our own plans for investment which would enable greater management and importation of goods because there is an overall freight dynamic for the island, not just sand and aggregates, and the increasing elements mean there are capacity constraints for us as an island so in order to safeguard that operation for the island we have a plan now which will significantly increase our capacity and enable the importation of products moving forward.”

Mr Tanner however added the facility would need to be “quite substantially” expanded to allow the importation of bulk materials, which he said would be “very expensive”, and that the importation of aggregates could cause issues.

VIdeo: On Wednesday, Chartered Town Planner Jeff Salt looked into the proposal extension of quarries.

“We had originally built plans around aggregates as well but obviously there was a change in terms of permits around aggregates, but obviously there would be some capacity around aggregates in the future,” he said.

“You could see challenge if there was significant change around the importation of aggregates on island but from a sand perspective we have plans.”

Mr Salt questioned what would the implications for the port if the expansion of the quarry at La Gigoulande didn’t go ahead and the quarry stopped its activity in seven years, which would require the importation of up to 100,000 tonnes of crushed granite products a year.

“If it happened now, it would be a significant problem from a capacity perspective but presuming that we progress with our plans and by 2024 we should have capacity to take on quite a considerable large volume of freight, which would enable us to do some of that."

However, he added: "...If it was complete importation of aggregates [260,000 tonnes, ed.], we would struggle,” Mr Tanner replied.

St_Helier_harbour_gov_of_Jsy.png

Pictured: Mr Tanner said the planned expansion of the port would help increase capacity.

He then added: “We do have longer term plans that we could develop that would enable that but it would be some way into the distance. Looking at the importation that would be required based on the volumes that are shared in the island report, which we agree with from our own work, I think that gradual change in freight requirements around aggregates is something that we would absorb in the short-term.”

Gregor Mutchi of Granite Products reminded the planning inspector that the importation of coarser aggregates in bulk is harder to accommodate than the importation of aggregates and sand and would require the creation of a processing area. 

“It breaks down in the cargo as you take it across, so if you are taking in 100,000 tones through the port, the island would have to look at how we actually process that once they got into the island to put it back into specification,” he said.

“You would need somewhere for screening that and processing that. I don’t know if you would have that near the port or whether you would carry that somewhere else to process it, but you can’t make the assumption that you can import it as a finished product, it’s not like a car, it actually breaks down into smaller sizes in the cargo.”

READ MORE...

Residents pledge to fight St. Peter's Valley quarry expansion

Discussions before £1.65m field sale to be made public

Artist draws on talents to fight quarry expansion

St. Ouen's Bay quarry "shocked" over plan to shut it by 2024

Bid to cut quarry expansion from Island Plan

INSIGHT: Island Plan...what the people REALLY care about

Sign up to newsletter

 

Comments

Comments on this story express the views of the commentator only, not Bailiwick Publishing. We are unable to guarantee the accuracy of any of those comments.

You have landed on the Bailiwick Express website, however it appears you are based in . Would you like to stay on the site, or visit the site?