Tuesday 23 April 2024
Select a region
News

WATCH: Specialists sent over after Nightingale storm damage

WATCH: Specialists sent over after Nightingale storm damage

Wednesday 08 July 2020

WATCH: Specialists sent over after Nightingale storm damage

Wednesday 08 July 2020


Recent heavy rains caused such damage to Jersey’s Nightingale Hospital that specialists from the Dutch company that erected it have had to be sent over to fix the problem, Express can reveal.

Two operatives from building contactors Neptunus arrived on the island last week to fix seals between panelling on the building that were torn apart after the facility was battered by high-speed winds and torrential rain in late June.

The damage resulted in water leaking into the facility.

While officials initially suggested there had been flooding in response to questions from Express, they downplayed the leakage in a fresh statement issued this afternoon, saying that only “some water” entered the building and that it had been cleaned up “with a mop”.

They declined to comment on how much was spent on clean-up and repair costs, arguing that they were “wrapped up” in the overall project costs and “difficult to separate out”.

Video: The Nightingale was affected by torrential rain and high winds on 25 June.

They noted, however, that the project remained “on budget”.

These are estimated to be at £14.4m, including a contingency funding pot of £1.3m.

The 180-bed hospital was built at Milbrook playing fields in a bid to provide additional bed capacity as part of the Government’s response to the covid-19 pandemic.

It includes areas for patient admissions and discharge, staff changing and rest facilities, and a morgue. 

Construction started over the Easter weekend, with Neptunus bringing over eight trailers containing the temporary structure and a full team to fit together the 'flatpack' structure.

nightingalebeds.jpg

Pictured: The wing has capacity for 180 beds.

While the first few weeks of the field hospital's existence were relatively peaceful with virus cases dwindling to just a few in the community, it was recently flooded when heavy rains battered the island just two weeks ago.

On 25 June, after temperatures reached 32 degrees, a severe thunderstorm hit the island, bringing lightning, strong winds, torrential rain and flash flooding.

Several thunderstorm warnings were issued by Jersey Met, followed by several wind warnings in the days that followed. 

Following questions from Express, the Government confirmed there had been “water ingress” at the field hospital, which they said had been cleaned up by the facilities and security team on site.

But the issue was serious enough that technicians from Neptunus sent two operatives to rectify the problem on Thursday 2 July.

A spokesperson explained: "Following heavy rains in late June, some rubber seals between panels on the side of the temporary Nightingale Wing were affected. This resulted in some water entering the building... Two technicians from Neptunus arrived the following week to re-seal the panels. This was paid for the Neptunus. [sic]"

Express has asked whether the pair are still on the island and is awaiting a reply.

The government denied that the facility had suffered any rodent infestation following speculation on social media.

The flood damage is not the only hurdle the facility has had to overcome in recent weeks, with the building only recently becoming eligible to receive a fire safety certificate.

fire_service.jpeg

Pictured: The Nightingale Hospital still doesn't have a valid fire certificate.

Evacuation exercises held on 24 June prompted the Fire and Rescue Service to suggest some improvements, including additional fire training, and more patrols.

“Further to the successful evacuation exercises held on June 24, there has been some learning from the Departments involved, and minor improvements have been mutually agreed to the satisfaction of the Fire and Rescue Service,” Jason Masterman, Group Commander of the Fire Service said.

“The Fire and Rescue Service are now in a position to issue a Fire Certificate for the use of the structure as a temporary covid-19 hospital wing, as and when it is brought into use.

“We will continue to work with Health and Social Services and play a role in any further planned evacuation exercises.”

-20200505nightingale024.jpg

Pictured: The Fire Service have suggested several improvements.

In May, the Fire and Rescue Service Association (FRSA) voiced concerns about the fact the Fire Service had not been involved in the initial stages of planning, despite the field hospital clearly falling under the Fire Precautions Law.

They highlighted that the lack of contact would mean the Nightingale would require a “near-permanent onsite fire service crew” to satisfy the fire risk assessment, adding that the crew could be taken away from the site at times to respond to other incidents with on-call crews taking over, perhaps not immediately.

In a , the FRSA wrote: “The risk assessment may rate a fire at the Nightingale as high-impact but low-likelihood, although this situation sits awkwardly with the FRSA if the required fire cover cannot be fulfilled, as we understand, due to budgetary constraints alone.”

Sign up to newsletter

 

Comments

Comments on this story express the views of the commentator only, not Bailiwick Publishing. We are unable to guarantee the accuracy of any of those comments.

You have landed on the Bailiwick Express website, however it appears you are based in . Would you like to stay on the site, or visit the site?