“Replacing the existing cable, which failed in October 2018, will return Guernsey to importing 90% of its electricity from sustainable sources in France,” said Guernsey Electricity Project Manager, Sharon Watchorn. “As with the existing link, the new cable will come ashore at Greve de Lecq and Havelet Bay.

Pictured: Guernsey Electricity logo.
“We can assure islanders that the route has been carefully evaluated to ensure minimal impact on marine users and to optimise cable burial.
“The PLGR is an essential element of the project as it allows the route to be cleared so the cable can be laid safely and efficiently.”
NKT Victoria will return to the Channel Islands in early October to complete the installation. During that time, the existing cable will be switched off and Guernsey’s power will be generated through the Vale power station.
The new cable, which is 37.4km long and weighs 77kg per metre, is part of the infrastructure connection Guernsey to France, via Jersey.
Pictured top: Cable laying ship.