A ‘ground penetrating radar survey’ of land around the Bridge will help determine when long awaited building work in the area can start.

The site investigations are starting today, with ground conditions and drainage being checked ahead of any building work starting at Leale’s Yard or the nearby vinery sites which are also earmarked for residential developments.

  • Penetrative radar surveys will be carried out on Thursday 2 July and Friday 3 July.
  • Temporary road signs will be used to allow workers unrestricted safe movement.
  • From Monday 6 – Friday 10 July, bore holes and trial holes will be dug.
  • Some parking and pavement use may be suspended temporarily while the work is carried out.
  • There may be traffic delays during peak times.
  • Wherever possible, motorists and pedestrians are asked to find new routes or use different methods of travel while the surveys are carried out.

The risk of water ‘overtopping’ at the Bridge has been a “key consideration” when developing plans for building new homes at Leale’s Yard, Parc Le Lacheur (the old Kenilworth Vinery), the data park site, and others.

With clearance work finally due to get started at Leale’s Yard this year, it’s hoped work to plan for future flood defences can also start soon.

Deputy Adrian Gabriel, President of the Committee for the Environment & Infrastructure, said the survey work starting today will help move the whole project on to the next stage, which will include finalising the location and the detailed design of future flood defences.

“These investigations are about making sure the defence is located in the most appropriate area of the Bridge,” he explained.

“Spending time understanding the ground conditions, drainage and underground layout now is essential to reduce the risk of unexpected problems later which would cause greater disruption. These site investigations are commonplace before larger projects take place, to better ensure good value for money.

“The flood defence is important for unlocking housing, investment and regeneration around the Bridge, as well as helping to protect existing homes and businesses. We know the works will cause some disruption, and we are grateful for the patience of residents, businesses and road users while this work takes place to enable the delivery of housing. This is a necessary step to make sure the project is properly informed and delivers best value for the island.”

Pictured: The Saltpans development is also reliant on flood defences at the Bridge.

Work on flood defences at the Bridge has been in the planning for a few years with the previous E&I President calling it a “priority” in 2024.

At the time, Deputy Lindsay de Sausmarez said introducing flood defences would “enable much needed housing development to progress”.

Speaking more recently, the now Policy and Resources President said pushing ahead with plans for flood defences at the Bridge, and the clearance work at Leale’s Yard would see numerous benefits including “unlocking private investment, creating new spaces for business and the community, generating jobs and helping to bring more social and economic vibrancy back to this important part of the island”.